Voice Platform Migration Timeline

Migration Goals and Objectives

As a University, Northwestern's migration to the Cisco voice platform will steadily progress over a two year period beginning, fall quarter 2017.

Chart displaying goals meet for each quarter

Migration by Campus Building

The table below provides information about when University buildings are scheduled to migrate to the new phone system.

Information may be modified throughout the project as more information becomes available.

Fall 2017

Evanston Campus
Building Name Target Start Date Status
1007 Church November - December 2017 On hold due to renovation
405 Church December 2017 - January 2018 Pending
555 Clark November - December 2017 Planning - In progress
619 Clark November - December 2017 Planning - In progress
906-910 University November 2017 Pending
2020 Ridge October - December 2017 Planning - In progress
Annenberg October - November 2017 Complete
Kellogg Global Hub January - March 2017 Complete
Seeley Mudd Hall September - December 2017 In Progress

Winter 2018

Evanston Campus
Building Name  Target Start Date Status
1201 Davis March - April 2018
620 Lincoln March 2018
Annie May Swift Hall February - March 2018
Catalysis March - April 2018
Crowe February 2018 Pending
Cook March - April 2018
Dearborn Observatory March 2018
Deering Library February 2018 Pending
Ford February - March 2018
Hogan March 2018
John Evans Center February 2018
Kresge February 2018 Pending
Lunt Hall December 2017 Pending
Segal Visitors Center January - February 2018 Pending
Silverman Hall February - March 2018
University Library January - March 2018 Pending
Chicago Campus
Building Name  Target Start Date Status
Abbott Hall January - March 2018 Pending
Levy Mayer March 2018
Weiboldt January - March 2018 Pending

Spring 2018

Evanston Campus
Building Name Target Start Date Status
600 Haven April 2018
616 Noyes March 2018
617 Haven April 2018
618 Garrett April 2018
620 Library May 2018
625 Haven April 2018
626 Library May 2018
629 Noyes March 2018
630 Lincoln February - March 2018
633 Emerson March - May 2018
640 Lincoln February - March 2018
1823 Sherman May 2018
2040 Sheridan Road May 2018
2046 Sheridan Road May 2018
Block Museum April 2018
Locy April 2018
Louis Hall March - April 2018
Lutkin Hall April 2018
McCormick Foundation Center April - May 2018
North Campus Garage March - April 2018
Pancoe April 2018
Pick Staiger April - May 2018
Regenstein March - April 2018
Ryan Center for the Performing Arts March - May 2018
Ryan Hall January - March 2018
Tech February - September 2018
Wirtz Center for the Performing Arts March - April 2018
Chicago Campus
Building Name  Target Start Date Status
McCormick March - April 2018

Summer 2018

Evanston Campus
Building Name  Target Start Date Status
1800 Sherman May - September 2018
1801 Hinman May - June 2018
1914 Sheridan August 2018
1918 Sheridan July - August 2018
1922 Sheridan July - August 2018
1936 Sheridan July 2018
1940 Sheridan July 2018
2000 Sheridan June - July 2018
2006 Sheridan June 2018
2010 Sheridan June 2018
2016 Sheridan June 2018
617 Library May - June 2018
618 Library May - June 2018
629 Foster July 2018
Fisk Hall April - June 2018
Frances Searle May - July 2018
Harris Hall May - June 2018
Patten Gymnasium July 2018
SPAC June - July 2018
Swift-Cresap July - August 2018
Tech February - September 2018
University Hall June - July 2018

Fall 2018

Evanston Campus
Building Name Target Start Date Status
1800 Sherman February - September 2018
1801 Maple October - November 2018
1808 Chicago May - September 2018
1809 Chicago August - September 2018
1810-12 Chicago August - September 2018
1810-12 Hinman September - October 2018
1813 Hinman September - October 2018
1815 Chicago September 2018
1819 Hinman September - October 2018
1902 Sheridan September - October 2018
1908 Sheridan October 2018
2031 Sheridan October 2018
2601 Orrington October 2018
515 Clark October - November 2018
619 Emerson October - November 2018
625 Noyes November 2018
Allen Center October - November 2018
Andersen Hall TBD
Ryan Field TBD
Tech July - September 2018
Welsh Ryan Arena TBD

Winter 2019

Evanston Campus
Building Name  Target Start Date Status
720 University December 2018 - January 2019
1603 Orrington February 2019
1809 Chicago November - December 2018
2122 Sheridan Road December 2018 - January 2019
711 Elgin November - December 2018
Blomquist January 2019
Coon Nicolette November - December 2018
Chambers Hall December 2018 - January 2019
Outdoor Fields December 2018 - January 2019
Rebecca Crown Center December 2018 - January 2019
Sailing Center January - February 2019
Chicago Campus
Building Name  Target Start Date Status
375 E. Chicago November 2018 - February 2019
633 N. St. Clair November 2018 - February 2019
676 N. St. Claire April - May 2019
750 N. Lake Shore Drive November 2018 - February 2019
Morton Medical Research Building October - December 2019
Searle October - December 2019

Spring 2019

Evanston Campus
Building Name Target Start Date Status
Central Utility Plant April - May 2019
Millar/Parkes March - April 2019
Norris April - June 2019
Rebecca Crown Center March - May 2019
Scott Hall July 2019
Chicago Campus
Building Name  Target Start Date Status
625 N. Michigan February - March 2019
645 N. Michigan January - March 2019
750 N. Lake Shore Drive February - March 2019
McGaw Olson Pavilion December 2018 - April 2019

Summer 2019

Evanston Campus
Building Name  Target Start Date Status
Swift Hall July - August 2019
Rebecca Crown Center May - August 2019
Chicago Campus
Building Name  Target Start Date Status
680 N. Lake Shore Drive April - June 2019
750 N. Lake Shore Drive April - June 2019
Lurie June - August 2019
Tarry June - August 2019
Ward May - August 2019

Migration by School/Department

The chart below displays when individual schools and departments are scheduled to migrate to the new phone system. The migration time period is agreed upon by each University school/department and will be updated as more information becomes available. Click the image to view a larger version.

Image of Timeline by school and department

Last Updated: 14 November 2017